The Present Location of the College
SATTELLITE VIEW 12.23N ,8.24E

Present Situation
- THE SIZE OF THE OLD SITE IS 19ha
- THE OLD SITE IS COMPLETELY BUILT UP, NO SPACE FOR EXPANSION
- THE COLLEGE HAS GOTTEN NUC APPROVAL , RUNS DEGREE PROGRAMMES AND REQUIRES LAND FOR EXPANSION
- BEEN A TECHNICAL COLLEGE IS UNIQUE IN THE REGION
- THERE IS AN URGENT NEED FOR TECHNICAL EDUCATION TEACHERS TO TAKE CARE OF LARGE POPULATION IN THE REGION
New Land
- KANO STATE GOVERNMENT DONATED 600 HA OF LAND FREE OF CHARGE
- KNSG PAID COMPENSATION ON LAND AND STRUCTURES REMAINING ONLY PAYMENT FOR ECONOMIC TREES TO THE LOCAL INHABITANTS
- THE INABILITY OF THE COLLEGE TO TAKE POSSESSION OF THE LAND FOR OVER 30 YEARS CREATED SOME CHALLENGES BUT IS NOW BEEN GRADUALLY RESOLVED
THE COLLEGE HAS A NEW SITE OF 600 HECTRES ON GWARZO ROAD 4KM FROM THE OLD SITE

SATELLITE VIEW OF THE NEW SITE

SATELLITE VIEW FROM BICHI TO NEW SITE

MASTER PLAN PHASE1

DEVELOPMENTS AT THE NEW SITE
THE COLLEGE HAS STARTED DEVELOPING THE NEW SITE
- CONSTRUCTION OF AGRIC EDUCATION DEPT
- CONSTRUCTION OF ADULTS AND SPECIAL NEEDS EDUC
- CONSTRUCTION OF PHYSICAL & HEALTH EDUC DEPT
- CONSTRUCTION OF EARLY CHILDHOOD CARE EDUC
- BUSINESS & ENTREPREUNERSHIP EDUC. SCHOOL
- CONSTRUCTION OF PRIMARY EDUC SCHOOL
- CONSTRUCTION OF STUDENTS HOSTEL
- CONSTRUCTION OF PERIMETER FENCING & GATES
- CONSTRUCTION OF SECURITY HUTS
- TREES PLANTING
- ROAD CONSTRUCTION
CONSTRUCTION OF GATE & ROAD

CONSTRUCTIONS OF BUSINESS, & SPECIAL NEEDS EDUCATION

CONSTRUCTION OF PHYSICAL/HEALTH, PRIMARY & AGRIC EDUCTION BLOCKS

CONSTRUCTION OF 250 CAPACTY THEATRE

CONSTRUCTION OF ACADEMIC OFFICES

CHALLENGES AT NEW SITE: LARGE PONDS

CHALLENGES AT NEW SITE: LARGE PONDS & DITCHES


CHALLENGES AT NEW SITE: FLOODING

CHALLENGES AT NEW SITE: LARGE PONDS & DITCHES


CHALLENGES: LARGE DITCHES AT THE COLLEGE FENCES

CHALLENGES: POOR AND INADEQUATE ROAD NETWORK

CHALLENGES: POOR AND INADEQUATE ROAD NETWORK

CHALLENGES: POOR AND INADEQUATE ROAD NETWORK

PRAYER
THE COLLEGE REQUIRES N1.2B FUNDS FOR
- FLOODS CONTROL
- CONSTRUCTTION OF 10KM ROAD NETWORK & DRAINAGES
- COMPLETION OF CONSTRUCTION OF 8KM PERIMETER SECURITY FENCE